Five jobs are waiting for processing through two work centers. Their processing time (in minutes) at each work center is contained in the table below. Each job requires work center Alpha before work center Beta

According to Johnson's rule, which job should be scheduled first in the sequence?

Job Alpha Beta
R 20 10
S 25 35
T 50 20
U 15 35
V 55 75

A) R
B) S
C) T
D) U
E) V


D

Business

You might also like to view...

What are the two forms of preventive damage control measures?

What will be an ideal response?

Business

Journalize the following transactions for a merchandiser that uses the gross method for recording sales and a perpetual inventory system.

On January 8, inventory was sold for $7,000 on account. Credit terms were 2/15, n/30 (cost $5,500). On January 31, cash was received in full settlement of the January 8 sale. Omit explanations. What will be an ideal response?

Business

The recording of cash payments to the cash account will be done by entering the amount as a credit

Indicate whether the statement is true or false

Business

What determines the difference between a direct and an indirect cost?

A. Whether it is relevant to a particular decision. B. Whether it is related to manufacturing or nonmanufacturing activities. C. Whether it changes when activity levels change. D. Whether it can be traced to a specific cost object.

Business