Discuss the role that the first or initial schedule for a project can play in litigation involving delays. What assumptions must be valid for this role to be justified?

What will be an ideal response?


The first schedule developed for a project is often referred to as the "as
planned" schedule. It is ostensibly a portrayal of the way task performance was originally
envisioned. If this schedule is realistic, this is certainly a valid schedule against which to
make comparisons. The assumption is that the information is accurate. To be of value in
defending a delay claim, the schedule must bear a reasonable relationship to the events
that would likely have taken place had construction progressed as planned.

Trades & Technology

You might also like to view...

A(n) ____________________ reaction requires supplied heat for the reaction to occur.

Fill in the blank(s) with the appropriate word(s).

Trades & Technology

The purpose of _____ is to show the animal to its best ability.

Fill in the blank(s) with the appropriate word(s).

Trades & Technology

The volume of a cone is equal to ?r2h where r is the radius and h is the height of the cone.

Answer the following statement true (T) or false (F)

Trades & Technology

If the voltage at the output lead of a three-wire sensor decreases when the sensor is activated, it is a __________ device.

A. sourcing B. sinking

Trades & Technology