Use the project described in the table to determine the total resources required for this project during week 2 if a worker is expected to devote half-time (four hours per day) to this project
Assume that the project work is conducted on a 5-day-per-week basis.
Activity Duration Predecessor
A 5 days --
B 4 days A
C 5 days A
D 6 days B
E 6 days C, D
F 6 days E
A) 30 hours
B) 20 hours
C) 40 hours
D) 36 hours
C
You might also like to view...
The treasurer should prepare and sign a check only after a proper check authorization has been provided
Indicate whether the statement is true or false
The due diligence defense generally requires the defendant to show that he had reasonable grounds to believe and did believe that there were no untrue statements or material omissions
a. True b. False Indicate whether the statement is true or false
Reba is a director of Quantum Mechanix Corporation. Reba's rights, as a director, do not include a right to
a. indemnification. b. inspection. c. participation. d. self-dealing.
Characteristics of established growth companies include all of the following EXCEPT
A) high operating margins. B) steady earnings growth. C) adequate cash flow to service their debt. D) high dividend payout ratios.