A simple sequential project (each task must be completed before the next one can begin) has the time estimates (in days) shown below:



What is the probability that the project will be completed within 8.5 days? (Choose the closest answer.)rev: 08_07_2017_QC_CS-95018

 

A. 80 percent

B. 15 percent

C. 75 percent

D. 5 percent


B. 15 percent

Business

You might also like to view...

Costs for which of the following activities would not be included as part of research and development (R&D) costs?

A) ?testing in search for or evaluation of product or process alternatives. B) ?adaptation of an existing capability to a particular requirement or customer's need as part of a continuing commercial activity. C) searching for applications of new research findings or of other knowledge?. D) ?design, construction, and testing or preproduction prototypes and models.

Business

Which of the following is a communication principle that should be used in applying a win-win conflict resolution strategy?

A. use emotional rather than neutral terms B. make absolute statements C. ask closed-ended questions D. repeat key phrases for understanding

Business

The type of business that has only one owner is a:

a. partnership. b. corporation. c. sole proprietorship. d. merchandising business. e. manufacturing business.

Business

In the United States, individuals and corporations are the two entities that pay tax on business income.

Answer the following statement true (T) or false (F)

Business