Determine which activities should be crashed to shorten the project by 3 days. What is the cost?
What will be an ideal response?
Answer: Crash C by 1 day, E by 1 day, and then B by 1 day and E by an additional day. Total cost = $1400.
Crash schedule:
Path Normal time Crash C Crash E Crash B & E
ABF 18 18 18 17
CEDF 20 19 18 17
Cost: $300 $500 $600
You might also like to view...
The best financial structure is determined by finding the debt and equity mix that maximizes the
firm's cost of capital. Indicate whether the statement is true or false
Field Gardens and Gourmet Restaurant, Inc., enter into a contract for a sale of lettuce. When Field learns that Gourmet is insolvent, Field can stop delivery of the goods in transit
A. only if the quantity is at least a carload. B. only if the quantity is at least a planeload. C. only if the quantity is at least a truckload. D. regardless of the quantity.
The Foreign Sovereign Immunities Act broadly defines commercial activity.
Answer the following statement true (T) or false (F)
If a bank compounds savings accounts quarterly, the nominal rate will exceed the effective annual rate.
Answer the following statement true (T) or false (F)