A project being analyzed by PERT has 60 activities, 13 of which are on the critical path
If the estimated time along the critical path is 214 days with a project variance of 100, what is the probability that the project will take 224 days or more to complete?
A) near zero
B) 0.0126
C) 0.1587
D) 0.8413
E) 2.14
C
You might also like to view...
____________________ is the proportional allocation of the cost of natural resources to the units used up or depleted per accounting period.
Fill in the blank(s) with the appropriate word(s).
Purple Airlines has ordered 30 small jets from its supplier. The supplier has estimated the first aircraft will require 350 days of direct labor to manufacture and assemble. Based on past experience, the supplier estimates the learning curve to be 75%. Estimate the number of days of direct labor for the 15th jet aircraft.
A. 113.75 days B. 115.32 days C. 120.43 days D. 116.87 days
An individual's privacy is invaded if his or her likeness is used for commercial purposes without permission
Indicate whether the statement is true or false
Variable-rate loans tied to long-term rates expose you to more risk of rate changes than variable-rate loans tied to short-term rates
Indicate whether this statement is true or false.