The amount of time an activity can be delayed without delaying the entire project is known as _____.

a. critical time
b. slack time
c. project evaluation
d. project milestone


b. slack time
In a systems development project, each activity is assigned an earliest start time andan earliest finish time. Each activity is also allocated slack time, which is the amount oftime an activity can be delayed without delaying the entire project.

Computer Science & Information Technology

You might also like to view...

When the final value of an expression is assigned to a variable, it will be converted to

a. the smallest C++ data type b. the largest C++ data type c. the data type of the variable d. the data type of the expression e. None of these

Computer Science & Information Technology

The purpose of the ____ input step is to control the upcoming loop.

A. sentinel B. start C. begin D. priming

Computer Science & Information Technology

Which of the following is TRUE about a data source file in the final steps of the merge process?

A) A one page list can be generated from a data source with the Envelopes command. B) A data source file cannot be used to create multiple sets of form documents. C) A data source can be filtered prior to merging. D) A data source can be used only one time.

Computer Science & Information Technology

A DVI port transmits a video signal and is also called a DB-15 port.

Answer the following statement true (T) or false (F)

Computer Science & Information Technology