Use the project described in the table to determine the total resources required for activity D if a worker is expected to work half-time (four hours per day) on this project
Activity Duration Predecessor
A 5 days --
B 4 days A
C 5 days A
D 6 days B
E 6 days C, D
F 6 days E
A) 6 hours
B) 40 hours
C) 24 hours
D) 48 hours
C
You might also like to view...
Managers who believe the customer is the company's only true "profit center" consider the traditional organization chart to be obsolete
Indicate whether the statement is true or false
Explain the trade term "free on board."
What will be an ideal response?
A "capitalized cost reduction" on an auto lease
A) is positively related to your monthly payments. An increase in the capitalized cost reduction will increase the size of your monthly lease payments. B) may be no more than three times your monthly lease payment C) is an advanced payment on the lease. D) is equal to the difference between the actual resale value at the expiration of the lease and the estimated resale value.
According to the pay model, the strategic compensation decisions regarding objectives involve:
A. how open and transparent the pay decisions should be to all employees. B. how total compensation should be positioned against competitors. C. how compensation should support the business strategy and be adaptive to the cultural and regulatory pressures in a global environment. D. how the different types and levels of skills and work should be paid within the organization. E. how pay increases should be based.