Explain whether a constructor is released from liability if the owner's engineer approves the contractor's shop drawings
What will be an ideal response?
When a contractor is responsible for generating shop drawings or working drawings the contract should state that the contractor should check them for accuracy, and then the engineer will check them for accuracy, but the contractor is still responsible for performing work according to the contract.