If the most optimistic time for completing an activity is 1, the most likely time is 2, and the most pessimistic time is 4, then the estimated time for the activity is ______.
A. 2.17
B. 3.63
C. 5.38
D. 9.44
A. 2.17
You might also like to view...
Explain the difference between societal culture and business culture.
What will be an ideal response?
Which of the following is NOT a methodological challenge to evaluating OD efforts?
a. difficulty assessing what constituted an improvement b. lack of true comparison groups c. time lags d. having relevant data
Which of the following would be classified as a prevention cost on a quality cost report?
A. Technical support provided to suppliers. B. Net cost of spoilage. C. Debugging software errors. D. Disposal of defective products.
In an FOB Place of Destination shipment Title passes to the buyer: A) when the goods are tendered at the seller's loading dock
B) when goods are tendered to the buyer at the destination. C) when goods are tendered to the carrier. D) when the goods are identified by the seller.