If a project is expected to be completed in 68 days with a project variance of 9 days, what is the probability that the project will be completed between 63 to 70 days?

a. 100%
b. 95%
c. 90%
d. 70%


d. 70%

Business

You might also like to view...

Replacement discontinuance and disenchantment rejection occur in which stage of the innovation process?

A. persuasion B. decision C. implementation D. confirmation

Business

Asking or requiring employees to ______ is the quickest and easiest way to fix a labor shortage.

A. hire their friends B. work slower C. work overtime D. take vacation

Business

Employers have legal grounds for conducting drug tests because every employer has a legal right to ensure that employees perform their jobs competently and that no employee endangers the safety of other workers.

Answer the following statement true (T) or false (F)

Business

Powderhouse, Inc has two processes—Coloring Department and Mixing Department

The company sold 2,000 gallons of paint for $220,000, of which $150,000 was sold on account. The total cost of processing was $385,000 for 5,500 gallons of paint. What are the journal entries to record a sale if the company follows a process costing system? What will be an ideal response

Business