An activity has an optimistic time estimate of 25 days, a most likely estimate of 29 days, and a pessimistic estimate of 34 days. What is the expected duration of the activity?

A) Less than 31 days but greater than or equal to 29 days
B) Less than 29 days but greater than or equal to 27 days
C) Less than 27 days but greater than or equal to 25 days
D) Less than 25 days


A

Business

You might also like to view...

Shorter product life cycles are common in industries characterized by low level of competition

Indicate whether the statement is true or false

Business

ROMI models are developed over limited time periods, usually less than 18 months

Indicate whether the statement is true or false

Business

Both U.S. GAAP and IFRS require firms to report balance sheet accounts for the prior year in addition to the current year

Indicate whether the statement is true or false

Business

Which of the following guidelines is NOT suggested for bridging an initial pitch and gaining a commitment of media mentions from connectors?

A) Never take "no" for an answer. B) Follow-up promptly. C) Repeat follow-ups until the media respond. D) Stay on-message. E) Be flexible about your story ideas.

Business