How do you determine the number of joists required?
What will be an ideal response?
The number of joists (floor and ceiling) required for a project are determined by:
1. From the contract documents determine the size, spacing, and grade of framing required.
2. Divide the spacing of the joist into the length to be covered and add one.
3. Calculate the length of the joists; remember to include bearing at the end and the required lap.
You might also like to view...
Sound waves travel at a speed of approximately ____ ft/sec through the air at sea level.
A. 445 B. 900 C. 1130 D. 1270
A vehicle has a total weight of 3,500 pounds, with 1,925 pounds in the front of the vehicle. What percentage of the weight is in on the front wheels?
A) 55% B) 53% C) 45% D) None of these
A skin irritation that can be caused by exposure to cement is called _____
a) lime abrasion b) pozzolanic reaction c) cement dermatitis d) cement aggravation
As temperature increases, the resistance of a good conductor will
A) decrease. B) change to become zero. C) stay the same. D) increase.