Activities following a node
a. can begin as soon as any activity preceding the node has been completed.
b. have an earliest start time equal to the largest of the earliest finish times for all activities entering the node.
c. have a latest start time equal to the largest of the earliest finish times for all activities entering the node.
d. None of the alternatives is correct.
B
You might also like to view...
Companies with advanced manufacturing technology tend to have lower fixed costs.
Answer the following statement true (T) or false (F)
If a periodic physical inventory of property, plant, and equipment is taken, the individual responsible for the inventory should be independent of the custodial and record-keeping functions.
Answer the following statement true (T) or false (F)
A company had the following stockholders' equity on January 1: Common Stock ? $1 par value; 1,000,000 shares authorized, 350,000 shares issued and outstanding …………………….$ 350,000Paid-in capital in excess of par value, common stock ……....700,000Retained earnings ……………………………………………364,000Total stockholders' equity ……………………………………$1,414,000??On January 10, the company declared a 40% stock dividend to stockholders of record on January 25, to be distributed January 31. The market value of the stock on January 10 prior to the dividend was $20 per share. What is the book value per common share on February 1?
What will be an ideal response?
Ethics is ______.
A. a 20th-century phenomenon B. the result of political scandal C. a cost of doing business D. the result of the culture, education, and philosophy of management