Which of the following does NOT help describe a project network?
A. Provides the basis for scheduling labor and equipment
B. Highlights major deliverables and identifies their completion dates
C. Gives the times when activities can start and finish and when they can be delayed
D. Identifies critical activities
E. A graphic display of the flow and sequence of work through the project
Answer: B
You might also like to view...
An example of a disadvantage of using surveys is interviewer error
Indicate whether the statement is true or false
The two key economic factors reflecting a country's attractiveness as a market are its industrial structure and its ________
A) communication adaptation B) nontariff trade barriers C) exchange controls D) income distribution E) transportation systems
A firm that transfers its receivables in exchange for cash can
a. use its accounts receivable as collateral for a loan from a bank or other financial institution. b. factor its accounts receivable to a bank or other financial institution in exchange for cash. c. transfer the accounts receivable to a legally separate entity that issues debt securities to investors. d. use all of the above. e. use none of the above.
________ refers to a doctrine that says a plaintiff who is partially at fault for his or her own injury cannot recover against the negligent defendant.
A. Assumption of the risk B. Comparative fault C. Contributory negligence D. Comparative negligence