A seven activity project has the activity durations (in weeks) and costs shown in the table. In addition to the activity costs shown in the table, there is an additional daily fixed cost of $450. What is the least expensive project completion cost?

Activity
Predecessor Normal Duration
Normal Cost Crash Duration
Crash Cost
A -- 7 $2000 5 $3000
B -- 8 $1500 6 $2000
C A 12 $2500 10 $2900
D B 13 $3000 10 $4200
E B 15 $4000 12 $5500
F C, E 10 $3200 8 $4000
G D 7 $1800 6 $2200

A) $31,450
B) $31,900
C) $32,350
D) $32,700


Answer: C

Business

You might also like to view...

When a nation achieves autarky equilibrium,

a. input price equals final product price. b. labor productivity equals the wage rate. c. imports equal exports. d. production equals consumption.

Business

All of the following can provide evidence of an economic event except

a. source document b. turn-around document c. master document d. product document

Business

Salon Finish is test marketing its new smoothing shampoo by assessing consumer satisfaction in laboratory stores where hair is washed and blown dry. Salon Pro is using controlled test marketing in this scenario

Indicate whether the statement is true or false

Business

Differentiate between motivation, performance, and effectiveness. Discuss the relationship between the three concepts.

What will be an ideal response?

Business