Which of the following statements concerning work packages is NOT correct?
a. Work packages are the basis for subsequent project planning activities.
b. Work packages are the basis for subsequent project control activities.
c. Work packages are activity elements with detailed descriptions of tasks and dependencies
d. Work packages are the elements at the lowest level of the WBS.
C
You might also like to view...
When McDonald's comes up with a new drink or sandwich for its restaurants, it often markets it in a dozen or so of its outlets. When the company does this, it is engaged in
A. pretesting. B. test marketing. C. product launch. D. concept testing. E. product development.
Tukey's multiple comparison method is ____________________ (more/less) powerful than Fisher's LSD method
Fill in the blank(s) with correct word
Companies seeking globalization can review the guidelines developed by the Organisation for Economic Cooperation and Development on operating internationally to become a multinational enterprise.
Answer the following statement true (T) or false (F)
The heights (in cm) for a random sample of 60 males were measured. The sample mean is 166.55, the standard deviation is 12.57, the sample kurtosis is 0.12, and the sample skewness is ?0.23. The following table shows the heights subdivided into non-overlapping intervals.ClassObservedExpected piHeight < 150100.09150 ? Height < 16060.21160 ? Height < 170180.31170 ? Height < 180170.25Height ? 18090.14The heights are subdivided into five intervals. The degrees of freedom for the goodness-of-fit test for normality is ________.
A. 3 B. 4 C. 5 D. 2