What is the NPV of the Boeing 787 Dreamliner project? The Boeing 787-8 can carry 230 passengers up to 8,200 nautical miles at a cruising speed of mach 0.85. The Dreamliner is more comfortable for passengers because of higher cabin humidity
Boeing completed construction on its final assembly plant at time t = 0 for a total cost of $7B. Boeing has secured orders for 865 aircraft over the next five years (t = 1 to t = 5 ) for total proceeds of $138.4B ($160M per aircraft). The cost of building each plane is $140M. Assume that cash flows (sales and costs) occur at the end of each year starting one year after the assembly plant was completed. The project cash flows are shown in the table, below. What is the NPV of the project if Boeing's cost of capital is 10%? Calculate the NPV as of time t=0. (Round answer to the nearest million).
Year Capital Investment Annual Sales Annual Revenues Annual Costs Cash Flows
t = 0 $7,000M -7,000
t = 1 173 27,680 24,220 3,460
t = 2 173 27,680 24,220 3,460
t = 3 173 27,680 24,220 3,460
t = 4 173 27,680 24,220 3,460
t = 5 173 27,680 24,220 3,460
A) $6,116M
B) $8,069M
C) $8,780M
D) $8,967M
E) $13,116M
A
You might also like to view...
An arbitrary amount that is stated on the face of the stock certificate is_______________
Fill in the blank(s) with correct word
________ as a pay objective involves abiding by various federal, provincial, and territorial compensation laws and regulations.
A. Competitiveness B. Compliance C. Fairness D. Efficiency E. Alignment
T.L. Franklin Corporation has three costs: A, which is variable; B, which is fixed; and C, which is semivariable. The company uses the high-low method and extracted the following data from its accounting records: •At 180,000 hours of activity, Cost A totaled $2,610,000.•At 140,000 hours, the low point during the period, Cost C totaled $1,498,000; at 200,000 hours, the high point, Cost C's fixed portion amounted to $1.75 per hour.•At 160,000 hours of activity, the sum of Costs A, B, and C amounted to $8,162,000.Required: A. Compute the variable portion (total) of Cost C at 140,000 hours of activity.B. Compute Cost C (total) at 160,000 hours of activity.C. Compute Cost B (total) at 160,000 hours of activity.
What will be an ideal response?
Jennifer grants an access easement to Cynthia across her property. Jennifer has created an easement by necessity
Indicate whether the statement is true or false