A building requires 20 feet of the grade beam whose cross section is shown in Figure 11.42. Using a waste factor of 8 percent, determine the number of cubic yards of concrete needed to pour the grade beam.

What will be an ideal response?


First, find the cross-sectional area:

Cross-sectional area (sf) = 12? × 14? /(12 in per ft)2 = 1.167 sf

Volume in grade beam (cy) = 20? × 1.167 sf = 23.34 cf / 27 cf per cy = 0.86 cy

Add 8% waste and round off.

Volume in piers (cy) = 0.86 cy × 1.08 = 0.93 cy – Use 1 cy

Trades & Technology

You might also like to view...

Equipment necessary to manufacture adjustable ball-lock pins for pulling two components together had a cost of $185,000 when the FRED Equipment Cost Index was 210.0. What was the estimated cost of a similar system in 2015 when the index value was 245.9?

What will be an ideal response?

Trades & Technology

Electronic control circuits can protect a system from a "low voltage" condition better than electromechanical controls.

Answer the following statement true (T) or false (F)

Trades & Technology

What type of scale ruler is used most often in plumbing work?

A. metric B. engineer's C. mechanic's D. architect's

Trades & Technology

One mile equals ____________________ yards.

Fill in the blank(s) with the appropriate word(s).

Trades & Technology