A project is composed of the twelve activities shown in the table. What are the earliest and latest start times for each of these activities?

Activity Time (days) Predecessors
A 3 --
B 3 A
C 15 A
D 2 B
E 12 B
F 16 C
G 2 C
H 11 E, F
I 9 D, G
J 6 D, E
K 15 H, I
L 13 J, K
What will be an ideal response?


Answer:
Activity ES LS
A 0 0
B 3 19
C 3 3
D 6 34
E 6 22
F 18 18
G 18 34
H 34 34
I 20 36
J 18 54
K 45 45
L 60 60

Business

You might also like to view...

Which of the following is an informal method used by marketers to evaluate connectors?

A) asking customers and other practitioners to identify promotional channels. B) having connectors answer in-depth, personal questionnaires. C) determining whether connectors will agree to carry product placement messages. D) meeting with each connector on an individual basis. E) hiring an investigative firm to conduct background checks.

Business

A bond that had a 20-year original maturity with 1 year left to maturity has more price risk than a 10-year original maturity bond with 1 year left to maturity. (Assume that the bonds have equal default risk and equal coupon rates, and they cannot be called.)

Answer the following statement true (T) or false (F)

Business

The VP of finance usually has the ______________________________ and the ______________________________ directly reporting to him (her).

Fill in the blank(s) with the appropriate word(s).

Business

Answer the following statement(s) true (T) or false (F)

1. High-power distance cultures are comfortable with differences in status. 2. Collectivist societies prefer universal ethical standards. 3. Masculine cultures maintain clearly defined sex roles. 4. Bribery is more common in collectivist societies. 5. Individualists are more likely to lie to protect the group or family.

Business