Calhoun Corporation's order quantity for Material T is 5,000 lbs. The company maintains a safety stock of T at 500 lbs., and its order point is 1,500 lbs. Refer to Calhoun Corporation. What is the lead time assuming daily usage is 50 lbs.?

a. 30 days
b. 100 days
c. 10 days
d. 20 days


D
Order point = (Daily use * Lead time) + Safety Stock
1,500 = (50 * LT) + 500
1,000 = (50 * LT)
20 = LT

Business

You might also like to view...

The process costing system that computes equivalent units only on work done in the current period is known as a __________________________________________________

Fill in the blank(s) with correct word

Business

African Americans will make up about 50 percent of the U.S. civilian workforce by the year 2018.

Answer the following statement true (T) or false (F)

Business

Tangible benefits arising from project implementation using CIM principles include a shorter manufacturing cycle time, lower inventory, lower project reject rate, and increased customer satisfaction

Indicate whether the statement is true or false

Business

The newest theory in social responsibility is called sustainability.  Explain what this means.

What will be an ideal response?

Business