Use the project described in the table to determine the total resources required for this project on day 2 if a worker is expected to devote half-time (four hours per day) to this project

Activity Duration Predecessor
A 5 days --
B 4 days A
C 5 days A
D 6 days B
E 6 days C, D
F 6 days E
A) 4 hours
B) 2 hours
C) 8 hours
D) 6 hours


A

Business

You might also like to view...

An arbitrary amount that is stated on the face of the stock certificate is_______________

Fill in the blank(s) with correct word

Business

Discuss the primary advantages and disadvantages that Citigroup obtained by merging with Travelers.

What will be an ideal response?

Business

A scholar who critiqued the traditional bureaucratic model depicted how ______________ became the dominant managerial paradigm, which he aptly described as an overrationalized view of organizational life.

a. neutralizing b. positive thinking c. humanism d. administrative rationality

Business

A clothing chain is considering two different locations for a new retail outlet. The organization has identified the four factors listed in the following table as the basis for evaluation, and it has assigned weights as shown

The manager has rated each location on each factor, on a 100-point basis (higher scores are better), as shown under the respective columns for Barclay and Chester. a. Calculate the composite score for each alternative location. b. Which site should be chosen? c. Are you concerned about the sensitivity and subjectivity of this solution? Comment. Factor Factor Description Weight Barclay Chester 1 Average community income .40 75 70 2 Community growth potential .25 60 80 3 Availability of public transportation .15 45 90 4 Labor cost .20 80 60

Business