How should the estimator handle any errors or omissions that may be found in the contract documents?

What will be an ideal response?


Errors in the specifications should be carefully noted in the estimator’s notebook. Most contract documents require that any request for interpretation and addenda be made within a certain number of days before the bid opening.

Trades & Technology

You might also like to view...

For the bridge network in Fig. 3.86, find i? using mesh analysis.

Trades & Technology

Tools are secured in the tailstock spin spindle:

A) With a spindle clamp B) By their Morse taper shanks C) With a quick-change holder D) With a set screw

Trades & Technology

The 3D Orbit tool is used mainly to:

a. Rotate objects in the 3D space b. Change the viewing point c. Place some objects closer to others d. Relocate the UCS

Trades & Technology

A vacuum pump is used by a technician to:

A. Remove air from the system after repairs have been performed B. Remove moisture from the system after repairs have been performed C. Remove refrigerant from the air conditioning system D. Both A and B are correct

Trades & Technology