Which of the following does 29 CFR 1910.178 not require?
A) Refresher training
B) Annual assessment of forklift operator performance
C) Initial training for operators
D) Evaluation of forklift operator performance at least every three years
B) Annual assessment of forklift operator performance
You might also like to view...
Square -edged floor sheathing requires an additional panel over it, which is typically a 1/4-in.-thick sanded plywood or hardboard, to make it a two-layer (combination) floor sheathing. Why is (additional) panel overlayment required?
What will be an ideal response?
A cam lobe–type motor could be:
a. only one speed b. completely variable speed c. used for only high-speed applications d. high or low speed
The capacitor of an RC integrator charges to ________ if the input is a 10 V pulse with a pulse width equal to one time constant
A) 6.3 V B) 3.7 VC C) 5 V D) 10 V
Precast concrete ____ obtain the information they need to prepare framing plans from architectural plans, engineers' sketches, or contractors' sketches.
A. CAD technicians B. CAD managers C. checkers D. drafting clerks