Progress payments are made to the contractor based upon:
A. an estimate of the work done as submitted by the resident project representative.
B. a predetermined payment schedule based upon the progress schedule.
C. the contractor's estimate of the work done each month.
D. invoices submitted to the resident project representative.
E. none of the above.
A