In the context of the Critical Path Method (CPM), the slack time (ST) for an activity is computed as:
A) the latest start (LS) time minus the earliest finish (EF) time.
B) the latest finish (LF) time minus the earliest start (ES) time.
C) the latest start (LS) time minus the earliest start (ES) time.
D) the earliest finish (EF) time minus the latest start (LS) time.
C
You might also like to view...
Which president led the antitrust reform movement?
A. Theodore Roosevelt B. Woodrow Wilson C. Harry Truman D. Franklin Roosevelt
An organization should be especially cautious about using MPR when ________
A) the economy is in a downturn and marketing budgets are low B) the firm is concurrently running advertising campaigns C) return on investment is inherently unpredictable D) the message of the firm is not particularly newsworthy E) the public relations function is overseen by the legal department
Punitive damages are found
A. throughout legal systems based on common law. B. in the U.S., EU, and Asia. C. in both secular and religious-based legal systems. D. only in the U.S.
A rule that governs the internal processes of an administrative agency is called a(n) ________
A) substantive rule B) internal law C) procedural rule D) executive law