What are the earliest activity start time and latest activity start time, and how are they computed?
What will be an ideal response?
The earliest start time (ES) is the earliest time at which an activity may start and still satisfy all precedence requirements. ES = Max{EF of all immediate predecessors}. The latest start time is the latest time at which an activity may start and still satisfy both precedence requirements and the overall project completion time. LS = LF - Activity time.
You might also like to view...
A potential benefit of cloud computing is that the client firm does not need to know where its data are bring processed
Indicate whether the statement is true or false
What are critical questions that managers should ask when determining the cost of downtime?
A. What is the productivity cost associated with each hour of downtime? B. How many transactions can the company afford to lose without significantly harming business? C. All of these D. None of these
Par value
a. is established for a share of stock after it is issued. b. is the legal capital established for a share of stock. c. represents what a share of stock is worth. d. represents the original selling price for a share of stock.
Although the boom in telecommunications and computer technology has spurred the growth of direct marketing in the United States, it has not had the same effect worldwide.
Answer the following statement true (T) or false (F)