All of the following are benefits of scheduling resources before project implementation EXCEPT

A. The project completion date can be established.
B. Work packages can be time-phased.
C. It allows managers to share resources with other project managers if it is requested without negatively impacting their project.
D. It ensures low network sensitivity.
E. It allows time for considering reasonable options if resource constraints do exist.


Answer: D

Business

You might also like to view...

Social conditions of routine, unchallenging, boring jobs tend to suppress the human faculties of rational and autonomous choice.

Answer the following statement true (T) or false (F)

Business

Picture Puzzle Company The Picture Puzzle Company has the following estimates for producing a single batch of 500 custom-made puzzles: Wait time 10 days Inspection time 1 hour Processing time 3 days Move time 1 day Refer to the Picture Puzzle Company information above. The total value-added time is:

A) 14 days and 1 hour. B) 13 days. C) 3 days. D) 4 days.

Business

A process range chart illustrates the amount of dispersion within the samples

Indicate whether the statement is true or false

Business

Refer to Instruction 13.1. At the end of the year the investor sells his stock that now has an average price per share of €57. What is the investor's average rate of return before converting the stock back into dollars?

A) 5.0% B) -3.0% C) -5.0% D) 3.0%

Business