What would be the estimated time for completion if time estimates for installation are as follows? optimistic = 1 week; pessimistic = 1 week; realistic = 1 week

A) 5 weeks
B) 12 weeks
C) 6 weeks
D) 3 weeks
E) 1 week


E
Explanation: E) You would use realistic time.

Business

You might also like to view...

Russell Co. received a $400 utility bill for the current month's electricity. It is not due until the end of the next month which is when they intend to pay it. Which of the following general journal entries will Russell Co. make to record the receipt of the bill?

A.

Cash400 
Utilities Expense 400

B.
Accounts Payable400 
Utilities Expense 400

C.
Utilities Expense400 
Accounts Receivable 400

D.
Utilities Expense400 
Accounts Payable 400

E. No journal entry is required.

Business

What is meant by the term "resource fit" as it applies to evaluating a diversified company's business lineup?

What will be an ideal response?

Business

Personal attributes that vary from one person to another are called

A. individual differences. B. organizational inducements. C. employee contributions. D. stressors. E. psychological contracts.

Business

A person who detains someone for shoplifting

a. may be liable for false imprisonment if she/he holds a suspected shoplifter for an unreasonably long period of time. b. is always liable for detaining a suspected shoplifter who turns out to be innocent. c. cannot be held liable for false imprisonment if the suspect had shoplifted store merchandise in the past. d. is legally required to be a licensed security guard.

Business