An observer has recorded the following select ( ) for a five-part task and has applied a rating factor (RF) to each. The times are in seconds
If there is a 15 percent allowance for "nonproductive" activities, compute the standard time for the total task.
Element RF
1 6.2 0.9
2 1.7 1.1
3 4.5 1.2
4 1.2 0.8
5 5.0 1.2
The standard time for the task is:
A) fewer than or equal to 21 seconds.
B) greater than 21 seconds but fewer than or equal to 23 seconds.
C) greater than 23 seconds but fewer than or equal to 25 seconds.
D) greater than 25 seconds.
B
You might also like to view...
Below is financial data for Fawnsworth Industries' current year. Net sales on account during year $500,000 Cost of merchandise sold during year 300,000 Accounts receivable, beginning of year 45,000 Accounts receivable, end of year 35,000 Inventory, beginning of year 90,000 Inventory, end of year 110,000 Refer to the data for Fawnsworth Industries. Based on this information, what is Fawnsworth's
inventory turnover ratio for the current period? a. 1.67 times b. 2.73 times c. 0.33 times d. 3.00 times
Failure to live up to a standard of care may be an act or an omission
a. True b. False Indicate whether the statement is true or false
SQL is a ________
A) data sublanguage B) data manipulation language C) data definition language D) programming language
Morrison Supply provides the following information about resources: Cost Driver RateCost Driver VolumeResources used Administrative$50 1,200administrative hoursCustomer service 310 65returnsEnergy 80 770machine hoursLong-term labor 90 1,600labor hoursMaterials 12 50,000unitsPurchasing 145 120purchase ordersSetups 450 115setups Resources used Administrative$68,000 Customer service 31,200 Energy 66,480 Long-term labor 163,000 Materials 625,000 Purchasing 34,000 Setups 60,400 Required:Compute the unused resource capacity for each preceding item.
What will be an ideal response?