In the t = (a + 4m + b)/6 calculation for expected activity completion time, the a refers to?

a. Optimistic completion time
b. Pessimistic completion time
c. Most likely completion time
d. Activity completion time variance


a. Optimistic completion time

Business

You might also like to view...

The most important influence on international HRM is the culture of the country in which a facility is located.

Answer the following statement true (T) or false (F)

Business

When a leader is able to get people to coalesce around team-based goals and the good of the greater organization, rather than focus on their own goals within the organization, this is called ______.

a. motivation b. synergy c. leadership by wandering around d. formal leadership

Business

Assess the attractiveness of the U.S. food service industry in 1994.

What will be an ideal response?

Business

Managerial accounting reports are prepared according to generally accepted accounting principles

Indicate whether the statement is true or false

Business