It is a good practice to have the person who will be responsible for performing activities in a project estimate the duration for other activities to be completed by other resources although the person might not have experience with those activities

a. True
b. False
Indicate whether the statement is true or false


False

Business

You might also like to view...

Assume that in your hand you hold an ordinary six-sided die and a dime. You toss both the die and the dime on a table. a.What is the probability that a head appears on the dime and a six on the die?b.What is the probability that a tail appears on the dime and any number more than 3 on the die?c.What is the probability that a number larger than 2 appears on the die?

What will be an ideal response?

Business

Which of the following is true of form messages??

A) ?They produce receiver reaction that is highly unfavorable. B) ?They tend to be too personal. C) ?They cannot be personalized. D) ?They are a fast way of transmitting recurring messages.

Business

Holo Company reported the following financial numbers for one of its divisions for the year; average total assets of $5,800,000; sales of $5,375,000; cost of goods sold of $3,225,000; and operating expenses of $1,147,000. Compute the division's return on investment:

A. 21.3%. B. 17.3%. C. 14.7%. D. 18.6%. E. 10.4%.

Business

A major weakness of a matrix organizational structure for project management occurs when:

A) The environment is dynamic. B) Resources are scarce and shared between functional responsibilities and the competing project. C) The number of human resource coordination meetings is considered. D) One considers the dual importance of project management and functional efficiency.

Business