Which of the following statements regarding the gross material requirements plan is TRUE?

A) It shows total demand for an item.
B) It shows when an item must be ordered from a supplier or when production must be started.
C) It combines a master production schedule with the time-phased schedule.
D) It requires several inputs, including an accurate bill of material.
E) All of the above are true.


E

Business

You might also like to view...

Social media are not effective intercultural communication tools because they only reinforce cultural differences

Indicate whether the statement is true or false

Business

An individual can claim harassment for comments directed against his or her homosexuality

Indicate whether the statement is true or false

Business

The locus of the portfolios in expected return-standard deviation space that have the minimum variance for each expected return is called

A) mean-variance efficient. B) MVE portfolio. C) mean standard deviation frontier. D) efficient frontier.

Business

The following data have been recorded for recently completed Job 450 on its job cost sheet. Direct materials cost was $3,044. A total of 46 direct labor-hours and 104 machine-hours were worked on the job. The direct labor wage rate is $15 per labor-hour. The Corporation applies manufacturing overhead on the basis of machine-hours. The predetermined overhead rate is $13 per machine-hour. The total cost for the job on its job cost sheet would be:

A. $5,086 B. $3,734 C. $3,072 D. $4,332

Business