A PERT/CPM activity has an optimistic time estimate of 4 days, a most likely time estimate of 6 days, and a pessimistic time estimate of 10 days. The expected time (in days) of this activity is:

A) 6.0.
B) 6.33.
C) 7.0.
D) 7.5.


Answer: B

Business

You might also like to view...

For buzz marketing to be successful, the brand must stand out and have a distinct advantage over current products on the market

Indicate whether the statement is true or false

Business

McDonald Corp owns a building with an original cost of $2,000,000 and accumulated depreciation at the balance sheet date of $300,000 . Based on a recent appraisal, the fair value of the building is $1,800,000. REQUIRED: 1 . At what amount will the

building be reported on the year-end balance sheet if McDonald follows U.S. GAAP? 2 . Does McDonald have a choice in the amount to report for the building if instead it follows IFRS? What are those choices?

Business

Imagine you are in the fundraising task group of your club, and you are raising funds for Alzheimer’s awareness. Describe what might occur in the performing stage of small group development.

What will be an ideal response?

Business

The organizational structure for the project team, including policies and procedures, is the:

A) Work breakdown structure. B) Rules statement. C) Scope statement. D) Management plan.

Business