The critical path is the shortest path through a network and indicates activities that cannot be delayed without delaying the project.

Answer the following statement true (T) or false (F)


False

Critical path means the path(s) with the longest duration through the network. If an activity on the critical path is delayed, the project is delayed the same amount of time.

Business

You might also like to view...

If a marketing researcher decides to use a Likert scale, the researcher has chosen a technique wherein the respondent reviews a statement that shows the amount of agreement/disagreement with some product, service, or concept

Indicate whether the statement is true or false

Business

The Bledsoe Marketing Research group has been hired to administer a series of questions to shoppers in a local mall. If questions on the survey questionnaire have only two possible responses (such as "yes/no"), what type of questions are these?

What will be an ideal response?

Business

The prepurchase stage begins with ____________

a. perceived risk b. formation of expectations c. moments of truth d. evoked set e. need arousal

Business

At the marriage of her daughter, Lorna is given papers to sign, which the catering company says are the invoices for the food, service, and decorations. Underneath the invoices are a carbon and a contract of sale for a portion of the failing catering business. Lorna signs the papers; her signature is transferred to the sales contract. This is a void contract because it was entered by fraud in the

execution. a. True b. False Indicate whether the statement is true or false

Business