Describe all activities that must occur in order to produce a Risk Mitigation, Monitoring, and Management Plan.
What will be an ideal response?
Risk Identification - determine the risks that are appropriate
Risk Projection - determine the likelihood that each risk will occur and the damage likely to occur
Risk Mitigation - figuring out strategies to avoid the risks
Risk Management and Contingency Planning - assuming each risk becomes a reality determine ways to limit their impact