When you receive the contractor's monthly partial payment request on a unit-price project, the engineer or resident project representative should:

A. just initial the form and forward it to the owner as no field review is necessary.
B. reject it.
C. check only the contractor's arithmetic on its payment request, while you "eyeball" estimate the amount of work completed to see if it appears to compare favorably with the contractor's claim.
D. check all of the contractor's field quantities accurately, along with all materials delivered to the site, and the contractor's claims to percentages of the various parts of the work completed.
E. check all of the contractor's field quantities within reasonable percentages of completion, along with all materials delivered to the site.


D

Trades & Technology

You might also like to view...

The automatic sprinkler system in a building is a part of

A) active fire protection. B) basic fire protection C) passive fire protection. D) upgraded fire protection E) none of the above.

Trades & Technology

Light energy, according to one theory of physics, is transmitted by small particles known as ____.

a. atoms b. photons c. electrons d. photoelectrons

Trades & Technology

Torque is expressed in units of _________

A) Pound-feet B) Foot-pounds per minute C) Pounds per minute D) Pound-feet per second

Trades & Technology

Mesh openings in a safety net are limited to _____.

a. 3" on the side b. 4" on the side c. 5" on the side d. 6" on the side