What strategy might a contractor employ on a small project to cover small extras, rather than comply with the excessively formal requirements set forth by the court in the Watson case?

What will be an ideal response?


Rather than comply with the excessively formal requirements set forth by
the court in the Watson case, a contractor in a small project, such as that
involved in Watson, might better add a contingency in the contract price to
cover small extras that are very likely to be requested.

Trades & Technology

You might also like to view...

In North Carolina, spearheaded by the Scots-Irish, a small insurrection against eastern domination of the colony's affair was known as

A. Bacon's Rebellion. B. March of the Paxton Boys. C. Regulator Movement. D. Shays' Rebellion. E. Whiskey Rebellion.

Trades & Technology

The "budgie" is the most popular pet bird in the world

Indicate whether the statement is true or false

Trades & Technology

Which of the following is most directly involved in project safety?

A. contractor. B. owner. C. resident project representative. D. architect/engineer. E. construction manager.

Trades & Technology

In creating a schematic diagram, signal flow should proceed from ____.

A. top to bottom B. bottom to top C. left to right D. right to left

Trades & Technology