In the t = (a + 4m + b)/6 calculation for expected activity completion time, the m refers to?

a. Optimistic completion time
b. Pessimistic completion time
c. Most likely completion time
d. Activity completion time variance


c. Most likely completion time

Business

You might also like to view...

According to the worldwide revenue figures for 2014, Omnicom Group is the world's largest advertising organization

Indicate whether the statement is true or false

Business

Consider Figure 6.2. As a result of the South Korean subsidy, Mexicans find their consumer surplus

a. rising by $160. b. rising by $220. c. falling by $160. d. falling by $220.

Business

Often the more committed a company is to sustainability and environmental protection, the more dilemmas that can arise

Indicate whether the statement is true or false

Business

Most of the developing countries of Africa and Latin America are free from the environmental pollution of the heavily industrialized nations

Indicate whether the statement is true or false

Business