Builder Construction Company's projects extend over several years and collection of receivables is reasonably certain. Each project has a contract that specifies a price and the rights and obligations of all parties. Both the contractor and the customer are expected to fulfill their contractual obligations on each project. Reliable estimates can be made of the extent of progress and cost to
complete each project. The method that the company should use to account for construction revenue is
a. installment sales.
b. percentage-of-completion.
c. completed-contract.
d. cost recovery.
B
You might also like to view...
When a coworker from Japan makes little to no eye contact with you during a conversation, what can you infer?
A) The Japanese coworker is untrustworthy. B) The Japanese coworker is being polite. C) The Japanese coworker does not like you. D) The Japanese coworker is rude. E) The Japanese coworker is bored or disinterested.
Andrew showed up to every team meeting late and did not complete his part of the project. The rest of the team had to pick up the slack to complete the project on time. Despite his lack of contribution, Andrew received the same group incentive as everyone else on the team. This illustrates which disadvantage of group incentives?
A. Social loafing may occur. B. Individual output may be discounted. C. Outstanding performers may slacken efforts. D. Group infighting may arise.
Discuss the two categories of sexual harassment
What impact does the timing of weaning have on its success
a. The later the weaning process begins, the easier it is. b. The earlier the weaning process begins, the easier it is. c. The difficulty of weaning is not dependent on when it happens. d. The earlier the weaning process begins, the harder it is.