A project consists of seven independent tasks with processing times (in hours) given by 4, 5, 6, 7, 8, 9, and 12.Find the optimal finishing time Opt for N = 2 processors.

A. Opt = 27 hours
B. Opt = 24 hours
C. Opt = 25 hours
D. Opt = 23 hours
E. Opt = 26 hours


Answer: E

Mathematics

You might also like to view...

Use the shell method to find the volume of the solid generated by revolving the region bounded by the given curves about the given lines.,y = 4,x = 2; revolve about the line 

A. ?
B. ?
C. ?
D. ?

Mathematics

Perform the indicated operation.0.28 - 0.83

A. 0.2324 B. -1.01 C. -1.11 D. -0.55

Mathematics

Find all real numbers that satisfy the equation. Round approximate answers to 2 decimal places. = 

A. 14
B. 28
C.
D. 24.2

Mathematics

Solve the problem.The graph shows the average cost of a barrel of crude oil for the years 1981 to 1990 in constant 1996 dollars. Find the approximate average change in price from 1981 to 1986.1996 $/Barrel  Year

A. About -$9/year B. About -$4/year C. About -$37/year D. About -$15/year

Mathematics