According to Table 11-3, there are five activities in a PERT project. If the normal distribution were used to find the probability of finishing this project in 24 weeks or fewer, what mean and variance would be used?

A) 20 and 4.222
B) 30 and 5.222
C) 20 and 5.222
D) 30 and 4.222
E) 22.667 and 1.111


E

Business

You might also like to view...

When Jenna feels stress coming on during the workday, she takes a break to picture herself walking along a beach. In other words, Jenna uses ______ to relax on the job.

A. meditation B. muscle relaxation exercises C. deep breathing D. hibernation

Business

Products that appeal to mothers have evolved since mothers are no longer homogenous like before. Instead, there are traditional, blended, and nontraditional moms. This most likely reflects a change in their__________

Fill in the blanks with correct word.

Business

One dimension of GLOBE research on culturally based shared conceptions of leadership is ______, which refers to independent and individualistic leadership.

A. humane oriented B. team oriented C. autonomous D. participative

Business

Discuss the importance of the ending of a presentation

Business