If a project has an expected completion time of 15 weeks with a variance of 4 weeks, there is a 95% likelihood that the project will be completed by what time?

A. by 17.5 weeks
B. by 16.5 weeks
C. by 15.5 weeks
D. by 14.5 weeks


A. by 17.5 weeks

Business

You might also like to view...

Under the modified cash basis of accounting, accounts receivable are not entered in the accounting system

Indicate whether the statement is true or false

Business

A review of cross-cultural research on job satisfaction concluded that______.

A. satisfaction is dramatically different in countries outside the United States. B. satisfaction is unrelated to performance in countries outside the United States. C. satisfaction is unrelated to withdrawal behaviors in countries outside the United States. D. satisfaction is similar in countries outside the United States.

Business

Stories that consumers create and share about how they use products

A) typically are a large part of traditional advertising campaigns. B) are inconsistent and unreliable, and therefore should be ignored. C) help to fuel word-of-mouth communication. D) are generally considered to be outside of customers' brand experience. E) spread more efficiently using low-tech sales tactics.

Business

MPR professionals need to understand how the various areas of corporate communications interrelate so that communication efforts are properly coordinated

Indicate whether the statement is true or false

Business