List four things that it is important to know as you work with master project files and subproject files.
What will be an ideal response?
Any changes to subprojects are automatically updated in the master project and vice versa if all files are open and the user has read/write access to all files.
You can add tasks to both the subprojects and the master project from within the master project file.
If you expand a subproject and insert a new row in or below the tasks of that subproject, you are adding a new row directly to that subproject.
To make sure that you are working at the master project level (when you add or move master-level tasks, for example), collapse all of the inserted subprojects.
If you select the "Inserted projects are calculated like summary tasks" check box on the Schedule tab of the Options dialog box (which is the default), then all subproject calculations in the master project file are treated as summary tasks.
You might also like to view...
When more than one class is derived from a base class, the situation is called
A) polymorphism. B) population. C) multiplicity. D) encapsulation. E) None of the above
The ________ IP addressing scheme uses 128-bit addressing
Fill in the blank(s) with correct word
In the accompanying figure, which number indicates the event for which you want Flash to listen?
A. 2 B. 3 C. 5 D. 6
Tap the ____________________ key to recalculate an answer.
Fill in the blank(s) with the appropriate word(s).