For critical path activities, slack is equal to ________
Fill in the blank(s) with the appropriate word(s).
Answer: zero
You might also like to view...
Which of the following statements is not a responsibility of the shopping center property management firm?
A. Maintain the parking lots. B. Ensure that the parking lot has good lighting. C. Create special events to attract customers to the shopping center. D. Maintain the outdoor signage for the shopping center. E. Provide temporary holiday sales staff for retailers.
In addition to focusing on controls, COBIT 5 expands its scope by incorporating which of the following broad perspectives?
A. How IT can automate specific business processes. B. IT networking requirements. C. IT cost reductions. D. How IT brings value to the firm.
If the researcher uses the mean response for the missing value, he/she is using which option for the treatment of missing values?
A) returning to the field B) casewise deletion C) substitute an imputed response D) substitute a neutral value
Rodriguez Inc is considering a project that costs $200,000. The company expects the annual cash revenues to be $75,000 and annual expenses (including depreciation) to be $30,000. The project has a ten-year useful life and a residual value of $25,000. Assume Rodriguez Inc uses the straight-line method of depreciation. Using the above information for Rodriguez, the accounting rate of return for the
project is (Round your answer to a whole percent) A) 51 percent. B) 22 percent. C) 67 percent. D) 40 percent.