If the risk-free rate is 6 percent, the return on an average stock is 10 percent, and the beta of this project is 1.50, then the expected return from the project is _____.?

A. ?12%
B. ?24%
C. ?4%
D. ?19%
E. ?23%


Answer: A

Business

You might also like to view...

In a mechanistic organization,   

A. most communication is informal. B. many teams and task forces are operating simultaneously. C. authority is decentralized. D. tasks and rules are clearly specified. E. employees are joined through technology.

Business

Which of the following is a cash management arrangement with a bank whereby the organization's customers send payments directly to the client's bank, which deposits the remittance to the client's account?

a. Lockbox. b. Bank transfer. c. Imprest bank account. d. Imprest Account.

Business

Explain the difference between attachment and perfection

Business

With opportunity to perform, activity level refers to the ________.

A. number of trained tasks performed on the job B. critical nature of the trained tasks C. frequency with which trained tasks are performed on the job D. number of employees performing a similar trained task

Business