Two critical path activities are candidates for crashing on a CPM network. Activity details are in the table below. To cut one day from the project's duration, activity ________ should be crashed first, adding ________ to project cost

Activity Normal Time Normal Cost Crash Time Crash Cost One 8 days $6,000 6 days $6,800 Two 10 days $4,000 9 days $5,000 A) One; $400 B) One; $6,800 C) Two; $1,000 D) Two; $5,000 E) One or Two should be crashed; $1,400

Business

A(n) __________ loan is one in which the original lender sells shares to other parties

a. master b. syndicated c. participation d. attached

Business

Labeling is ____________ packaging.

A. always included on the back of B. always included on the front of C. never required on D. done independent of E. closely interrelated to

Business

If a wire manufacturing company owned a mill to produce the metal used in making the wire, this relationship between the companies would be best be described as: ______

A) a conglomerate. B) a holding company. C) an integrated industry. D) a merger.

Business