The first step in determining the elevations of building corners using a level and the site plan is to ________
A) Remove the lines from the batter boards
B) Set the first batter board at the lowest point of the building footprint
C) Use the 3-4-5 method of squaring the corners
D) Set the first batter board at the highest point of the building footprint
D