Activity A has a standard cost of $500 and the standard time to complete Activity A is 5 weeks. The crash time for Activity A is 3 weeks and the crash cost is $600. What is the crash cost per week for Activity A?

A) $50
B) $100
C) $150
D) $200
E) $300


A

Business

You might also like to view...

Why is an organization’s history important?

a. Organizations need to learn from their mistakes b. Organizations should try to repeat what worked for them in the past c. It provides insight into how the organization evolved and developed its mission, values, and strategy d. It’s useful to explain to customers and stakeholders and is a valuable marketing tool

Business

Risk retention for minor losses is a recommended risk management strategy

Indicate whether the statement is true or false.

Business

Which of the following would be considered an intangible?

a. clothing b. food c. hardware d. iTunes download

Business

What most likely happens when a firm optimizes its organizational structure to its current situation?

A. It transforms strategy into actions and business models. B. It achieves superior performance. C. It plants the seed of subsequent failure: the tightly coupled system can break apart when internal or external pressures occur. D. It makes it difficult for managers to make the necessary changes due to its effects on resource allocation and power distribution.

Business