The amount of time that an activity in a project network can be delayed without causing a delay to subsequent activities or project completion best defines
A) restricted flow.
B) task obstruction.
C) capacity.
D) slack.
D
You might also like to view...
In SPSS, if the data are interval scaled and only the summary statistics are desired, the DESCRIPTIVES procedure can be used
Indicate whether the statement is true or false
The ABC classification method classifies inventory based on ______.
a. unit value b. amount of safety stock needed c. product quality d. quantity demanded
Officers in the US military have no control over employee pay. It is all based on time of service and rank. The military uses medals and ribbons to acknowledge excellence. The medals are an example of
A. intangible rewards. B. job tasks. C. stressors. D. contributions. E. inducements.
The value of zero for beta coefficient of the risk-free asset reflects not only its absence of risk but also the fact that the asset's return is unaffected by movements in the market return
Indicate whether the statement is true or false